Construction Alert - Paterson, Wayne

ADVANCED CONSTRUCTION ALERT – PATERSON, WAYNE

These dates are for planning purposes and may be adjusted due to weather.  Updates will be posted as known.


MILLING AND PAVING OPERATIONS DURING THE MONTH OF JULY 2019

In all instances, work will begin with milling, followed with resetting of inlets and manholes and finally paving and striping.

– Weather Permitting –

HAMBURG TURNPIKE WEST-BOUND LANE FROM VICINITY OF CHURCH LANE TO PREAKNESS CENTER
Milling to be completed Monday night, July 15, 2019.
Paving is scheduled Thursday and Friday night, July 18 through 19, 2019.

STRAIGHT STREET FROM ELLISON TO 21st STREET
July 12 through 17, 2019 
Milling is scheduled for Thursday night, July 18, 2019.
Paving will be scheduled for next week.

E. 33rd STREET FROM BROADWAY TO THE PASSAIC RIVER
Milling to be completed on Tuesday and Wednesday night, July 16 through 17, 2019.
Paving will be scheduled for next week.


ALPS ROAD FROM MAPLE AVE TO NELLIS DRIVE
July 22 through 25

Paulison Avenue in Clifton has been eliminated from the program pending PSE&G work. 

Lane Shifts and Alternating Traffic will be maintained but short-term closures may be necessary. 

Between milling and paving, there will be rough pavement and raised manholes and inlets – travelers should slow down and drive with caution through the work zones.

We recommend travelers select alternate routes.

All travelers in these areas must remain alert to construction equipment and watch carefully for the safety of construction workers.