A Storm Drain Connection Permit is required to connect into the County Storm Drain system. Permits are needed in two cases:
County Planning Board Approval
If the connection in question is part of a site plan approved by the County Planning Board, then the applicant completes the Storm Drain Connection permit and submits it to the County Engineering Department. No plans are necessary. The permit will be processed and approved through the County Counsel Department.
No Planning Board Approval
If County Planning Board approval is not required, then the applicant must submit plans and drainage calculations, 25 year storm, along with the form to the Engineering Department. The proposal will be reviewed, and a letter sent to the applicant within 15 business days. The letter will either approve, deny the plan, or request modifications. There is no guarantee that approval will be granted.